TRAVEL ALERTS IN THE FREDERICKSBURG DISTRICT

Jan. 27 – Feb. 2, 2019

 

All work is scheduled weather permitting. Real-time information on work zones and lane closures is available on 511Virginia.

 

For more information about an individual project, you can either click the project title links below or visit the project page at www.VirginiaDOT.org

 

 

Interstate 95 Southbound Rappahannock River Crossing Project

 

Interstate 95 – Northbound

(New) Wednesday and Thursday, 9:30 a.m. – 3:30 p.m. Expect a single lane closure on I-95 northbound between mile marker 134 and mile marker 135 located between Exit 133 (Route 17/Falmouth) and Exit 136 (Centreport Parkway) in Stafford County.

 

Route 17 – Northbound (24-hour closure)

Be alert to the 24-hour closure of a single right lane on Route 17 northbound between Sanford Drive and Short Street in Stafford on Mondays through Fridays for project construction activities. The 24-hour closure is needed to allow crews to work safely with construction equipment near the on- and off-ramps, travel lanes and underneath the I-95 overpasses.

 

Route 17 – Southbound

Expect a single right lane closure on Route 17 southbound between Sanford Drive and Short Street for bridge construction.

 

·    Monday – Thursday, 7 a.m. – 3 p.m.

·     Friday, 7 a.m. – noon

 

Interstate 95 (Exit 140/Courthouse Road)

 

Courthouse Road Widening Work:

Monday – Thursday, 9 a.m. – 2:30 p.m. and Friday, 9 a.m. – 12 p.m. Expect brief delays with alternating, one-way traffic at the following locations:

 

·    Courthouse Road between Austin Ridge Drive and Mine Road, Cedar Lane to Walpole Street and Austin Ridge Drive to Red Oak Drive.

·    Liberty Knolls Drive

·    Ramoth Church Road

·    Snowbird Lane

·    Winding Creek Road

·    Woodcutters Road

·    Wyche Road

 

A flagging crew will direct drivers in each work zone.

 

Interstate 95 at Exit 118/Mudd Tavern Road Widening and Bridge Replacement Project

 

Mudd Tavern Road and Mallard Road

(Update) Monday – Thursday, 9 a.m. – 3:30 p.m. and Friday, 9 a.m. – 12 p.m. Expect alternating, one-way traffic on Mudd Tavern Road and Mallard Road near the interchange for construction. Flaggers will direct drivers through the work zone.

 

Stafford County Work Zones

 

Traffic Signal Inspections

(New) During the overnight hours on Thursday, Jan. 31, crews will be inspecting traffic signals at the following intersections in Stafford County. Drivers should expect mobile lane closures in each work zone. Inspections will take place between 9 p.m. – 5 a.m.

 

·      Route 1 (Northbound and Southbound) at Hospital Center Boulevard

·     Route 1706 (Plantation Drive) at Gladstone Drive/Lyons Boulevard

 

Route 3 Westbound 24-Hour Lane Closure 

(New) Beginning Monday, Jan. 28, a 24-hour single lane closure will begin on Route 3 westbound between James Ashby Parkway and Leonard Road in connection with a Stafford County utility project. This single lane closure is in addition to the single lane closure on Route 3 eastbound. The single lane closure on Route 3 westbound is expected to remain in place for approximately 30 days.

 

Route 3 Eastbound 24-Hour Lane Closure 

A single lane is closed on Route 3 eastbound between Leonard Road and James Ashby Parkway for a Stafford County utility project. The lane closure will remain for the duration of the county project.

 

Routine Maintenance

 

Monday − Friday, 7 a.m. – 3:30 p.m. Stay alert for mobile lane closures. Crews will perform routine maintenance activities at the following locations:

 

·    Route 607 (Cool Spring Road) – pothole patching

·    Route 608 (Brooke Road) – ditch cleaning

·    Route 624 (Layhill Road) – ditch cleaning

 

Spotsylvania County Work Zone

 

Traffic Signal Inspections on Route 620 (Harrison Road)

(New) During the overnight hours on Wednesday, Jan. 30, crews will be inspecting the traffic signals at the following intersections on Harrison Road. Drivers should expect mobile lane closures in each work zone. Inspections will take place between 9 p.m. – 5 a.m.

 

·    Route 620 (Harrison Road) at Route 1284 (Entrance to landfill)

·     Route 620 (Harrison Road) at Route 1344 (Kingswood Boulevard/Beauclaire Boulevard)

 

Route 1 (Jefferson Davis Highway) at I-95

(Update) Sunday – Thursday, 9 p.m. – 6 a.m. Expect alternating lane closures on Route 1 northbound and southbound at the I-95 overpasses for bridge repairs.

 

Caroline County Work Zones

 

Route 207 Eastbound

Monday – Friday, 7 a.m. – 5 p.m. Bridge repairs on Route 207 eastbound over Polecat Creek. Beam end repairs. Route 207 eastbound traffic will be reduced to a single lane. Work will be underway through late March 2019, weather permitting.

 

Americans with Disabilities Act (ADA) Ramp Repair

Monday ˗˗ Friday, 9 a.m. ˗˗ 5 p.m. Motorists should be alert to a mobile work zone with crews and construction equipment at the following intersections:

·    Route 1201 (Anderson Avenue) at Route 207 (W. Broaddus Avenue) and Route 619 (Milford Street)

·     Route 619 (Milford Street) at Route 207 (W. Broaddus Avenue) and Route 1209 (Coghill Street)

·     Route 619 (Chase Street) at Route 301 (N. Main Street) and Route 1206 (Butler Street)

·     Route 1204 (Courthouse Road) at Route 301 (N. Main Street) and Route 1206 (Butler Street)

 

Crews are making repairs to the ADA (Americans with Disabilities Act) ramps and pedestrian crossings on these routes. There may be temporary, alternating shoulder closures or flagging operations with this work.

 

Routine Maintenance

 

Monday − Friday, 7 a.m. – 3:30 p.m. Stay alert for mobile lane closures. Crews will perform routine maintenance activities at the following locations:

 

·    Route 603 (Countyline Church Road) – Ditch cleaning

·    Route 656 (Colemans Mill Road) – Ditch cleaning

 

Caroline County/King George County Work Zone

 

Route 301 at Rappahannock River (James Madison Bridge)

Monday − Friday, 7 a.m. – 7 p.m. Traffic will be reduced to a single lane on Route 301 northbound and southbound near the James Madison Bridge over the Rappahannock River for a bridge maintenance project. Expect brief delays on the bridge and at the bridge approaches.

 

Essex County Work Zone

 

Route 17

(New) Tuesday – Friday, 9 a.m. – 5 p.m. Expect brief delays at various locations on Route 17 northbound and southbound between Route 654 and the Middlesex County line. Crews will be replacing the reflective lens on the raised pavement markers. This is a slow-moving mobile operation. Drivers should use caution when approaching the work zone.

 

Middlesex County Work Zone

 

Route 17

(New) Monday – Friday, 9 a.m. – 5 p.m. Expect brief delays at various locations on Route 17 northbound and southbound between the Gloucester County line and the Essex County line. Crews will be replacing the reflective lens on the raised pavement markers. This is a slow moving mobile operation. Drivers should use caution when approaching the work zone.

 

Town of West Point Work Zones

 

Eltham Bridge

(Update) Monday, 9 a.m. – noon. Expect a single lane closure on the eastbound side of the Eltham Bridge while crews prepare for upcoming bridge maintenance work.

 

Lord Delaware Bridge

(Update) Monday, noon – 3 p.m.  Expect a single lane closure on the eastbound side of the Lord Delaware bridge while crews prepare for upcoming bridge maintenance work.

 

Other Fredericksburg District Projects

 

Stafford County

 

Route 608 (Brooke Road): ROAD CLOSED

Brooke Road is closed to through traffic near Eskimo Hill Road. This is a Stafford County project to realign the roadway to improve safety and drainage. The road will reopen by February 28, 2019. For more information about the project and the detour route, please visit the county’s project page.

 

Spotsylvania County

 

Route 658 (Mount Olive Road) Bridge Replacement: ROAD CLOSED

Construction is underway to build a replacement bridge on Route 658 (Mount Olive Road) over the North Anna River, which will restore a connection between Hanover County and Spotsylvania County. The new bridge is estimated to open in late February 2019. Visit the project page for additional details.

 

Lancaster County

 

Route 222 (Weems Road): ROAD CLOSED

Weems Road is closed to through traffic between Gaskins Road and Christ Church Road for an emergency project to replace a failed drainage pipe and reconstruct the road and travel surface. Detour signs have been posted to guide motorists through the work zone. The road is anticipated to reopen in late January 2019.

 

Emergency Road Repairs: Tropical Storm Michael

 

Emergency repair work continues to rebuild several state-maintained roads that sustained severe damage during Tropical Storm Michael. These roads require major reconstruction or replacement of pipes and culverts before they can safely be reopened. Emergency procurement methods are being used to expedite repairs.

 

Estimated construction schedules for the remaining closed roads in Fredericksburg District are listed below:

 

King William County

 

Route 662 (Sharon Road): Anticipated to reopen in August 2019. This is a new date from the previously estimated reopening date of Jan. 21, 2019. The original date was based on an initial damage assessment after the storm. Further inspection by VDOT structural engineers identified a broken drainage culvert at the site, which will require more complex and extensive repairs. Crews will reconstruct a slope near the road and repair the culvert.

 

Northumberland County

 

Route 201 (Courthouse Road): Anticipated to reopen in June 2019. This is a new date from the previously estimated reopening date of Feb. 28, 2019. Crews are replacing a damaged set of four 96-inch drainage pipes with a triple set of concrete box culverts, with each culvert measuring 12 feet by 10 feet. The replacement culverts are larger than originally estimated, which has resulted in a longer fabrication period. The culverts must be fabricated to these specific dimensions, which lengthens the repair schedule.

 

Route 634 (Spring Road): Anticipated to reopen in August 2019. Crews are repairing the bridge and replacing a washed out section of road.

 

Route 642 (Knights Run Road): Anticipated to reopen in late February 2019. Crews will be replacing two 60-inch drainage pipes with two 72-inch reinforced concrete drainage pipes, and installing pipe headwalls.

 

Stafford County

 

Route 1350 (Hamlin Drive): Anticipated to reopen in April 2019. This is a new date from the previously estimated reopening date of Jan. 31, 2019. Crews are repairing a void underneath the travel surface and replacing a damaged 72-inch corrugated metal drainage pipe with a 6 foot by 6 foot concrete box culvert.

 

Westmoreland County

 

Route 600 (Nomini Grove Road): Anticipated to reopen in August 2019. Crews are repairing a void underneath the road and replacing a washed out section of road.

 

Route 612 (Antioch Road): Anticipated to reopen in August 2019. Crews are repairing a void underneath the road and replacing a washed out section of road.

 